671. The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation B. Scope planning C. Scope change control D. Scope Definition E. Scope verification ANS: D 672. The project charter is prepared in which scope management process? A. Initiation B. Scope planning C. Scope Definition D. Scope change control E. Scope verification ANS: A 673. In which of the following scope management processes is the scope management plan prepared? A. Initiation B. Scope planning C. Scope Definition D. Scope change control E. Scope verification ANS: B 674. Which of the following is not a scope management process? A. Initiation B. Scope planning C. Scope Definition D. Scope change control E. Scope verification ANS: D 675. The initial document that formally recognizes the existence of a project is the _____ . A. Scope baseline B. Management plan C. Project charter D. Configuration control report E. None of the above ANS: C 676. Which of the following are included as part of a scope statement? A. Project justification B. Project deliverables C. Project objectives D. All of the above E. B and C ANS: D 677. Project life cycles are very useful for _____ and _____ . A. Configuration management, termination B. Objective setting, information gathering C. Standardization, control D. Configuration management, weekly status updates E. Approval, termination ANS: C 678. Work packages are used to: A. Represent units of work at a level where work is performed. B. Clearly distinguish one work package from all others assigned to a single functional group. C. Limit the work to be performed to relatively short periods of time. D. All of the above. E. A and B only ANS: D 679. "Hard logic" in the preparation of a network refers to: A. Discretionay dependencies B. External depenencies C. Mandatory dependencies D. All of the above E. A abd B only ANS: C 680. The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency. A. Discretionary B. Mandatory C. External D. Soft logic E. Subcontracted ANS: B 681. Sources for data on activity durations and resource requirements can be gathered from which of the following: A. Past project records (historical data) B. Commercial techniques (standard practices, rules of thumb) C. Past project team members knowledge (experience, oldtimers) D. All of the above E. A and C only ANS: D 682. Which of the following can affect network durations? A. Skills of the resource pool B. Calendar dates C. Constraints D. All of the above E. A and B only ANS: E 683. A completion of a local government study resides on your critical path. This would most likely be referred to as: A. Soft logic B. Hard logic C. An external dependency D. A mandatory dependency E. A lost cause ANS: C
|
|