661. Using the table in the Special window, Which task is completed? A. dig hole B. remove debris C. survey D. set forms E. place concrete ANS: B 662. Using the situation stated in the Special window, what is the cost performance index for Case #9? A. 1.10 B. 1.91 C. 0.83 D. 1.20 E. None of the above ANS: A 663. Using the WBS shown in the Special window, a typical work package would be: A. Software development B. Systems design C. Coding D. A, B, and C E. None of the above. ANS: E 664. Which of the statements regarding benefit-cost analysis in the Special window are true? A. 1 and 2 B. 2 and 3 C. 1 and 3 D. 1, 2 and 3 E. None of the above. ANS: C 665. Using the cumulative cost curve in the special window, height B represents A. actual cost to date B. total budgeted costs for the project C. planned cost for month 6 D. cost variance E. earned value ANS: B 666. Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____. A. Become worse, become worse B. Become worse, improved C. Improved, increased D. Improved, become worse E. None of the above are correct ANS: B 667. Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is: A. K B. K C. K D. K E. indeterminate ANS: C 668. Using the scenario in the special window, the project manager appears to be a _____ manager. A. 1, 9 B. 9, 1 C. 1, 1 D. 9, 9 E. 5, 5 ANS: E 669. Using the scenario in the special window, the project manager: A. will probably spend the weekend reviewing the data. B. Won't ask for the report again. C. Has a preference for written communication. D. Has chosen an inappropriate medium. E. Is experiencing communication overload. ANS: E 670. In which of the following scope management processes are subject matter experts used? A. Initiation B. Scope planning C. Scope Definition D. Scope change control E. Scope verification ANS: A
|
|