631. Using the situation stated in the Special window, which WBS element is behind schedule but under budget? A. Element P B. Element Q C. Element R D. Element S E. None of the above. ANS: D 632. Using the situation stated in the Special window, which WBS element has a favorable cost variance of 0? A. Element P B. Element Q C. Element R D. Element S E. None of the above. ANS: C 633. Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is: A. 0.875 B. 1.14 C. 0.952 D. 0.833 E. 1.20 ANS: B 634. Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is: A. 1.10 B. 0.90 C. 0.956 D. 1.15 E. 0.869 ANS: A 635. Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent. A. Over, 16.66 B. Under, 16.66 C. Over, 10.0 D. Under, 10.0 E. None of the above. ANS: A 636. Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____. A. Become worse, become worse B. Become worse, improved C. Improved, increased D. Improved, become worse E. None of the above are correct ANS: E 637. Using the situation stated in the Special window, the total price variance of direct material is: A. ,245 B. -36 C. -79 D. %content%.69 E. ,994 ANS: C 638. Using the situation stated in the Special window, the labor rate cost variance is: A. ,927 B. ,329 C. 6 D. -%content%.22 E. .36 ANS: D 639. Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets? A. ,000 B. ,000 C. ,270 D. ,335 E. ,000 ANS: E 640. Using the figure in the Special window, The critical path is: A. A-B-G B. C-G C. C-D D. E-F E. A-B-G and C-D ANS: B
|
|