中国IT动力,最新最全的IT技术教程
最新100篇 | 推荐100篇 | 专题100篇 | 排行榜 | 搜索 | 在线API文档
首 页 | 程序开发 | 操作系统 | 软件应用 | 图形图象 | 网络应用 | 精文荟萃 | 教育认证 | 硬件维护 | 未整理篇 | 站长教程
ASP JS PHP工程 ASP.NET 网站建设 UML J2EESUN .NET VC VB VFP 网络维护 数据库 DB2 SQL2000 Oracle Mysql
服务器 Win2000 Office C DreamWeaver FireWorks Flash PhotoShop 上网宝典 CorelDraw 协议大全 网络安全 微软认证
硬件维护  CPU  主板  硬盘  内存  显卡  显示器  键盘鼠标  声卡音箱  打印机  机箱电源  BIOS  网卡  C#  Java  Delphi  vs.net2005
  当前位置:> 网络应用 > 上网宝典
PMP认证考试试题精选(53)
作者:佚名 时间:2003-10-10 08:39 出处:互连网 责编:chinaitpower
              摘要:PMP认证考试试题精选(53)

  521. Project management provides organizations with a methodology to:
  A. Become more efficient and effective in accomplishing goals that cannot be handled well by the traditional structure
  B. Manage high risk repetitive work
  C. Provide clients with multiple points of contact
  D. Provide guidance in accomplishing repetitive activities
  E. All of the above
  ANS: A
  
  522. Random cause or system variation is:
  A. generally present in every process
  B. the responsibility of the inspection of the process
  C. the responsibility of the workers of the process
  D. the responsibility of management
  E. A and D only
  ANS: E
  
  523. The most frequently used construct in Precedent Diagramming Method is:
  A. Start to Start.
  B. Finish to Finish.
  C. Start to Finish.
  D. Finish to Start.
  E. Dummy activity.
  ANS: D
  
  524. The person sending a message is NOT influenced by which of the following
  A. sender's credibility
  B. receiver's assumptions
  C. receiver's evaluative and tendency
  D. receiver's attitude and needs
  E. sender's knowledge
  ANS: C
  
  525. A common mistake in communications is to _____ of the receiver.
  A. overestimate the knowledge
  B. underestimate the knowledge
  C. underestimate the intelligence
  D. overestimate the intelligence
  E. None of the above.
  ANS: A
  
  526. A key to successful Management by Objectives (MBO) is
  A. insuring that employees have clearly defined objectives
  B. involving employees in decision meetings
  C. permitting employees to set their own objectives
  D. allowing employees to perform their own evaluations
  E. A or C.
  ANS: E
  
  527. Sunk costs are:
  A. future costs held in reserve.
  B. costs invested in commodities.
  C. expended costs over which we have no control.
  D. expended costs over which we have no more control
  E. tax credits
  ANS: D
  
  528. The degree to which a company accepts and utilizes project management is often dependent upon the _____ and _____ of the project.
  A. Competition, dollar value
  B. Type of industry, manpower requirements
  C. Size, nature
  D. Quality requirements, manpower requirement
  E. Type of industry, risk
  ANS: C
  
  529. The specification for a particular part is 10" + or - 0.015". The standard associated process produces parts with a means of 10" and standard
  deviation of 0.002'. The process capability index is:
  A. 0.002
  B. 1.0
  C. 2.5
  D. 7.5
  E. None of the above
  ANS: C
  
  530. Which of the following is indicative of negative float?
  A. The late start date is earlier than the early start date.
  B. The critical path supports the imposed end date.
  C. The early finish date is equal to the late finish date.
  D. When leads are employed in the schedule.
  E. The project is sinking.
  ANS: A
  
  
  
  
  
  