PMP认证考试试题精选(44)
作者:佚名 时间:2003-10-10 08:39 出处:互连网 责编:chinaitpower
              摘要:PMP认证考试试题精选(44)

  441. The schedule risk is the _____ .
  A. the accumulated "expected' durations which maintain project completion.
  B. Critical Path adjusted by "high-risk" activity float.
  C. highest risk path that maintains quality.
  D. Critical Path when calculated with "most likely" duration.
  E. highest risk path that contributes the most risk toward the project completion.
  ANS: B
  
  442. Screening of risk events for potential risk is known as _____ .
  A. problem structuring.
  B. risk identification
  C. risk quantification
  D. risk modeling
  E. risk mitigation
  ANS: B
  
  443. The Cost Performance Index is computed as:
  A. budget cost of work performed divided by actual cost of work performed
  B. budget cost of work performed minus actual cost of work performed
  C. budget cost of work performed minus budget cost of work scheduled
  D. budget cost of work scheduled divided by budget cost of work performed
  E. actual cost of work scheduled divided by budget cost of work performed
  ANS: A
  
  444. Typical characteristics of a work package include:
  A. Representation of units of work at a level where work is performed
  B. Clearly distinguishes one work package from all others assigned to a single functional group
  C. Limits the work to be performed to relatively short periods of time
  D. All of the above
  E. A and B only
  ANS: E
  
  445. Which of the following is not a cost of non-conformance?
  A. maintenance and calibration
  B. warranty repairs
  C. scrap
  D. rework
  E. All of the above.
  ANS: A
  
  446. Which of the following is not a method of government procurement.
  A. Assistance
  B. sealed bidding
  C. competitive proposals
  D. acquisition
  E. small purchases
  ANS: D
  
  447. Which of the following would most likely not be an essential objective of a project team kick-off meeting
  A. Create a project technology master plan
  B. Get team members to know one another
  C. Identify project problem areas
  D. Obtain individual and group commitments
  E. Identify the project coordinator
  ANS: A
  
  448. You are in a meeting with someone who just ate a slice of garlic bread. Your are distracted by his pungent breath. Which of the following
  communication barriers describe these distractions?
  A. Sign Detection
  B. Sensory Limitations
  C. Selective Perception
  D. Varying Alertness of Perception
  E. None of the above
  ANS: A
  
  449. Arbitration is a _____ approach to conflict management in resolving conflict disputes.
  A. lose-lose
  B. win-win
  C. win-lose
  D. lose-win
  E. closed door
  ANS: A
  
  450. As project manager, you wish to impose a standard method by which subordinates calculate project costs. Which level of communication
  should be required for this effort?
  A. Face-to-face
  B. Telephone
  C. Written
  D. Non-verbal
  E. All of the above should be required.
  ANS: C
  
  