341. Which of the following fall(s) under the responsibilities of a project manager? A. Labor relations with project personnel B. Affirmative action C. Personnel training D. Discrimination and equal employment opportunity E. All of the above ANS: E 342. A legally binding document offered unilaterally is a _____ . A. purchase order B. scope of work description C. contract stipulation D. level of effort proposal E. request for proposal ANS: A 343. A technical requirement has which of the following characteristics: A. easy to understand B. a communication tool between the user and the design team C. written in non-technical language D. developed in cooperation with the user E. typically describe physical dimensions and performance requirements ANS: E 344. If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume: A. the message was understood B. the message was not understood C. the subordinate discarded the information D. the information was not appropriate E. None of the above. ANS: E 345. Inspection of a complex project according to specifications is accomplished by _____. A. inspection by attributes. B. cyclical inspection C. quality conformance inspection D. original inspection E. None of the above. ANS: C 346. The behavioral responsibilities of a project manager may also include dealing with: A. The public B. Regulatory personnel C. The legal environment D. Environmental issues E. All of the above ANS: E 347. The difference between the BCWS and the BCWP is referred to as the: A. Schedule variance B. Cost variance. C. Estimate of completion D. Actual cost of the work performed E. None of the above ANS: A 348. "Paraphrasing" is most closely associated with which part of the communication process? A. encoding B. decoding C. barriers D. feedback E. None of the above. ANS: D 349. A Gantt chart is useful in determining: A. the level of effort for a task B. when a task starts and stops C. how tasks are related to each other D. who is assigned to do a task E. All of the above. ANS: B 350. A contract originated bilaterally may be developed by _____ . A. quotation request from suppliers B. proposal request C. bid invitation release D. B and C E. All of the above. ANS: E
|
|