中国IT动力,最新最全的IT技术教程
最新100篇 | 推荐100篇 | 专题100篇 | 排行榜 | 搜索 | 在线API文档 | 网通镜像
首 页 | 程序开发 | 操作系统 | 软件应用 | 图形图象 | 网络应用 | 精文荟萃 | 教育认证 | 硬件维护 | 未整理篇 | 站长教程
ASP JS PHP工程 ASP.NET 网站建设 UML J2EESUN .NET VC VB VFP 网络维护 数据库 DB2 SQL2000 Oracle Mysql
服务器 Win2000 Office C DreamWeaver FireWorks Flash PhotoShop 上网宝典 CorelDraw 协议大全 网络安全 微软认证
硬件维护  CPU  主板  硬盘  内存  显卡  显示器  键盘鼠标  声卡音箱  打印机  机箱电源  BIOS  网卡  C#  Java  Delphi  vs.net2005
  当前位置:> 网络应用 > 上网宝典
PMP认证考试试题精选(7)
作者:佚名 时间:2003-10-10 08:39 出处:互连网 责编:chinaitpower
              摘要:PMP认证考试试题精选(7)

  121. Valid reasons for considering termination of a project include all of the following except:
   A. The scope of the project is found to be inconsistent
   with the organization?s financial strength
   B. Organizational support is being spread among too many projects
   C. Scope change requests are numerous and continuous
   D. The project product has become available as a commercial off the shelf product
  
   ANS: C
   Reference: Project Management: A Managerial Approach, 2000 p.545
  
   122. Project termination responsibilities include all of the following except:
   A. Ensure the completion of work
   B. Notify the client of completion and ensure delivery of the product
   C. Ensure that documentation is complete
   D. Ensure that the project baseline is updated to reflect actual project perfonmnce
  
   ANS: D
   Reference: Project Management: A Managerial Approach, 2000 p. 555-556
  
   123. Project termination responsibilities include all of the following except:
   A. Modify project quality standards to reflect those actually implemented
   B. Oversee preparation of final invoices for the client
   C. Redistribute personnel, materials, equipment, and other resources
   D. Record and archive all legal project documents
  
   ANS: A
   Reference: Project Management: A Managerial Approach, 2000 p. 555-556
  
   124. Project termination responsibilities include all of the following except:
   A. Archive appropriate project documentation
   B. Provide project personnel with favorable perfonmnce appraisals to ensure
   their future cooperation
   C. Ensure the fulfillment of product support requirements
   D. Oversee the closing of project accounting
  
   ANS: B
   Reference: Project Management: A Managerial Approach, 2000 p.555-556
  
   125. Which equation conectly illustrates the cost variance of a project, in dollars?
   A. BCWP-ACWP
   B. BCWP/ACWP
   C. BCWP-BCWS
   D. BCWP/BCWS
  
   ANS: A
   Reference: PMBOK Figure 10-3, 10.3.2.4
  
   126. The 揟o Complete Performance Index?(TCPI) is calculated by:
   A. Subtracting the actual costs to date from the estimate at completion
   B. Dividing the budgeted cost of the remaining work by the difference between the
   estimate at completion and actual costs to date
   C. Multiplying the estimate at completion by the cumulative cost performance index
   D. Adding the estimate at completion to the actual costs to
   date and multiplying by the cumulative cost perfonmnce index
  
   ANS: B
   Reference: Earned Value Project Management p. 138
  
   127. At 40% through your project you havea BCWS of ,000 and a BCWP of ,000. Your
   project is:
   A. Ahead of schedule
   B. Behind schedule
   C. A positive cost variance
   D. A negative cost variance
  
   ANS: B
   Reference: PMBOK 10.3.2.4
  
   128. Under what knowledge area is the primary process area for canying out the work of the
   project?
   A. Scope
   B. Integration
   C. Schedule
   D. Framework
  
   ANS: B
   Reference: PMBOK4.2
  
   129. Which of the following is not true about Project Plan Development?
   A. Wait until all the other planning outputs are complete, then compile them into
   one final project plan
   B. It is used to document project planning assumptions
   C. It is an iterative process
   D. It involves making trade offs between competing objectives and alternatives
  
   ANS: A
   Reference: PMBOK4.1
  
   130. Coordinating a schedule, organizational policies, staffing plans and historical
   information about risk is an example of:
   A. Overall change control
   B. Risk management
   C. Communication planning
   D. Project plan development
  
   ANS: D
   Reference: PMBOK4.1.1
  
   131. Afactor that limits the project team?s options, such as a prescribed due date, is called a:
   A. Risk
   B. Constraint
   C. Assumption
   D. Hassle
  
   ANS: B
   Reference: PMBOK4.1.1.4
  
   132. Those areas that a project manager considers to be true, real or certain are called:
   A. Constraints
   B. Risks
   C. Assumptions
   D. Planning levers
  
   ANS: c
   Reference: PMBOK4.1.1.5
  
   133. You are a new project manager at a utility. In working on your first project you are refenlng
   to the project templates, company glossary, ABT Workbench Manual, and archives from
   previous projects. These tools are helping you with:
   A. Project plan coordination
   B. Project plan execution
   C. Project planning methodology
   D. The ?soft? tools of project management
  
   ANS: c
   Reference: PMBOK4.1.2.1
  
   134. As a project manager on a major construction project you spend some time informally
   interviewing contractors, teammembers, engineers and even some of the city permit people.
   You want to make sure you have all your bases covered in the planning process. This is an
   example of
   A. Information gathering and distribution
   B. Risk analysis
   C. Developing a project management information system
   D. Gathering stakeholder skills and knowledge
  
   ANS: D
   Reference: PMBOK4.1.2.2
  
   135. Project files, project software, and shared folders are examples of
   A. Project management information system
   B. Communication management
   C. Communication planning
   D. Risk management tools
  
   ANS: A
   Reference: PMBOK4.1.2.3
  
   136. A collection of documents that will change over time as more information becomes available
   is called:
   A. A project baseline
   B. A project plan
   C. A project management infonmtion system
   D. A management control
  
   ANS: B
   Reference: PMBOK4.1.3.1
  
   137. A management control that rarely changes, and then only in response to defined criteria,
   such as a change in scope is called a:
   A. Project plan
   B. Change management plan
   C. Project baseline
   D. A subsidiary management plan
  
   ANS: c
   Reference: PMBOK4.1.3.1
  
   138. Which of the following is not an appropriate reason to provide members of
   your project team with additional training?
   A. Feedback from other project managers about team performance
   B. Reports about performance that do not meet project requirements
   C. Excessive overtime requirements in order to meet the project schedule
   D. New technologies involved in the scope of the project
  
   ANS: C
   Reference: PMBOK9.3.2.5
  
   139. Team development is undertaken to improve performance.
   Which of the following is not a way in which team development improves team performance?
   A. Improvement of individual skills
   B. Development of technical breakthroughs
   C. Improvement of team behaviors
   D. Development of better ways of doing work
  
   ANS: B
   Reference: PMBOK9.3.3
  
   140. As project manager, you prepare written input to the performance appraisals of functional
   personnel assigned to your project. This activity is a part of which human resources process?
   A. Perfonmnce reporting
   B. Staffing pool description
   C. Team development
   D. Organizational planning
  
   ANS: C
   Reference: PMBOK9.3.3.2
  
关闭本页
 
首页 | 投资与合作 | 服务条款 | 隐私政策 | 收藏本站 | 设为首页 | 新用户注册 | 免责声明 | 使用帮助
Copyright ©2005-2008 chinaitpower.com All rights reserved. www.chinaitpower.com 版权所有